ouya Clinic project

Exterior view of a 3D-rendered medical building from the back.
Exterior view of a 3D-rendered medical building from the front.
Interior view of a 3D-rendered medical building from side 1.
Interior view of a 3D-rendered medical building from side 2.
Floor plan for a medical building. Includes a large waiting room surrounded by 13 rooms with various purposes.

The Ouya Clinic will be constructed from several storage containers, resulting in a final building approximately 16 by 11 meters in size. The clinic will feature the following rooms:

  • Laboratory

  • Office

  • Consultation

  • Pharmacy

  • Triage

  • Admin

  • Storage

  • HIV counseling

  • Prayer room

  • 2x Wards

  • ANC

  • Vaccination

  • Waiting room

September 17, 2026

On September 17th, installation of the plumbing systems began. Pipes were laid in the ground surrounding the clinic and attached to the shipping containers in preparation for sinks and toilets.

September 12, 2026

September 12th, 2026 saw the arrival of two of the shipping containers after a long 8 hour journey from the fabrication company. The trucks drove to the site of the clinic, where they were placed in accordance with the floor plan.

Placing the first shipping container

A crane lowering a shipping container onto the ground.

Two shipping containers are positioned on the slab

Updates

Three people are standing in a courtyard surrounded by three shipping containers.

Positioning the shipping container on the slab

Two large trucks transporting two shipping containers.

Arrival of the first two shipping containers

September 14, 2026

On September 14th, the third and final shipping container arrived. The 20-footer was placed on the slab, connecting the two 40-footer containers that arrived two days prior. The clinic base was assembled and is awaiting roofing.

A shipping container on a truck bed.

The 20-footer shipping container finally arrived

Progress of the plumbing system setup

Exterior of a shipping container showing green pipes attached for plumbing.

Attachments for the plumbing system

Pipes in the ground surrounding a shipping container.

Plumbing system laid out and pipes set up

Three shipping containers assembled in a U-shape on a foundation.

Fully assembled and waiting for a roof

Updates

September 17, 2026

On September 17th, installation of the plumbing systems began. Pipes were laid in the ground surrounding the clinic and attached to the shipping containers in preparation for sinks and toilets.

Progress of the plumbing system setup

Exterior of a shipping container showing green pipes attached for plumbing.

Attachments for the plumbing system

Pipes in the ground surrounding a shipping container.

Plumbing system laid out and pipes set up

September 14, 2026

On September 14th, the third and final shipping container arrived. The 20-footer was placed on the slab, connecting the two 40-footer containers that arrived two days prior. The clinic base was assembled and is awaiting roofing.

Three shipping containers assembled in a U-shape on a foundation.

Fully assembled and waiting for a roof

A shipping container on a truck bed.

The 20-footer shipping container finally arrived

Three people are standing in a courtyard surrounded by three shipping containers.

Positioning the shipping container on the slab

September 12, 2026

September 12th, 2026 saw the arrival of two of the shipping containers after a long 8 hour journey from the fabrication company. The trucks drove to the site of the clinic, where they were placed in accordance with the floor plan.

Placing the first shipping container

A crane lowering a shipping container onto the ground.

Two shipping containers are positioned on the slab

Two large trucks transporting two shipping containers.

Arrival of the first two shipping containers